Case Study

Weaverham WWTW

Green Asset Lab Enabling Works

V J Donegan & Co Ltd received an enquiry from Costain to design and build for a 25m x 25m hardstanding area to support 8 no. Reactive Media Tanks along with 2 no. CSO Wetland tanks.

These tanks were to be supplied by pumps at three separate locations around the WwTW, which would be controlled within a welfare unit next to the slab.

This work was required to provide United Utilities with a temporary Green Asset Lab that could be used for future testing of sewerage running through the WwTW.

Details

Client: Costain / United Utilities

Services Provided

General Civil Engineering

Reinforced Concrete Structures

Tunnelling and Pipejacking

Weaverham
Weaverham
Weaverham

Scope of Works

  • Construct a reinforced concrete slab 25.00m x 25.00m
  • Construct hardstanding area to the side of the slab with 2 no. welfare units connected to mains supply and sewer.
  • Install ducting from slab to three pump locations situated around the WwTW for power cabling and telemetry.
  • Construct crane pad and provide cranage for the installation of CSO storage tanks on the concrete slab.
  • Installation of pumps at three locations, a mains distribution board on the concrete slab and a control panel within the welfare unit to control supply to the tanks.

Other Projects

Mancunian Way, Manchester

Balfour Beatty / United Utilities

Segmental Shaft Sinking

Dewar Place Cable Tunnel

Edinburgh

Segmental Shaft Sinking

Failsworth WwTW (LiMA)

LiMA for United Utilities

Sheet Piling

Contact Us

Contact us for more information about this project or for estimation on your projects