Case Study
Crow Lane, Chesterfield
This project was carried out in partnership with E.T.M. for Yorkshire Water.
The Contract included the sinking and construction of a 15.00m diameter shaft to a depth of approx 25 meters, giving over 3,500m3 / 3.5million litres of storage capacity for storm water.



Scope of Works at Crow Lane, Chesterfield
- Sinking and construction of a 15m diameter shaft 25m deep
Other Projects
Mancunian Way, Manchester
Balfour Beatty / United Utilities
Segmental Shaft Sinking
Dewar Place Cable Tunnel
Edinburgh
Segmental Shaft Sinking
New Victoria, Manchester
For Vinci
General Civil Engineering
Contact Us