Case Study
Langdale Way, Frodsham
This project was carried out on behalf of Balfour Beatty, for United Utilities.
The Contract included the sinking and construction of a 20.00m diameter shaft approx 17m deep, and a 9.00m diameter shaft approx 10m deep, within the playing field of a primary school.
Details
Client: Balfour Beatty / United Utilities
Services Provided
Scope of Works at Langdale Way, Frodsham
- Sinking and construction of a 20m diameter shaft 17m deep
- Sinking and construction of a 9m diameter shaft 10m deep
Other Projects
Mancunian Way, Manchester
Balfour Beatty / United Utilities
Segmental Shaft Sinking
Dewar Place Cable Tunnel
Edinburgh
Segmental Shaft Sinking
New Victoria, Manchester
For Vinci
General Civil Engineering